Single-Girder Overhead Cranes Exported to Mexico for Injection Molding Workshop

Yuantai Cranes Mexico project: 5T and 10T HD single-girder cranes improve mold handling with custom design, VFD control, low headroom structure, and installation support.

From Workshop Survey to Final Operation: A Customized Mold Handling Solution

A Mexican injection molding factory needed two overhead cranes to improve its mold handling process.After expanding production capacity, the factory faced more frequent mold changes and heavier mold handling tasks. Moving molds manually became slower and created safety concerns.

The customer needed a safer and more efficient way to handle:

  • Heavy mold lifting
  • Mold replacement
  • Mold transfer between production stations

However, the customer had limited experience with crane systems. They needed support with crane selection, workshop measurement, installation planning, and final commissioning.Yuantai Cranes provided a complete project solution, starting from the first workshop survey:

  • Checked the existing building structure and installation conditions
  • Selected the suitable crane type based on the application
  • Designed a customized crane system
  • Manufactured and delivered the equipment
  • Supported installation and commissioning

Based on the actual workshop layout and lifting requirements, Yuantai Cranes supplied two HD single-girder overhead cranes for the Mexican injection molding workshop. The cranes are now operating reliably for daily mold handling operations.

Project Background

The customer is a Mexican injection molding manufacturer with multiple production lines.After expanding production capacity, the factory faced a new challenge.The number of mold changes increased.The mold weight also increased.Workers needed to frequently move molds between production stations.Manual handling became inefficient and created safety concerns.

The customer needed overhead cranes for:

  • Heavy mold lifting
  • Mold replacement
  • Mold flipping
  • Material transfer between production areas

However, the customer did not have crane engineering experience.They needed support with:

  • Workshop measurement
  • Crane structure selection
  • Installation planning
  • Operation requirements

Our engineers first studied the actual working conditions before designing the solution.

Site Survey: Problems Found Before Crane Design

Challenge 1: Existing Workshop Structure Was Not Ready for Crane Installation

During the workshop inspection, our engineers found that the existing building was not originally designed for overhead cranes.

The concrete corbels had several limitations:

  • No embedded steel plates on the corbels
  • No embedded components on column sides
  • Uneven installation surfaces
  • Missing corner support structures

The corbel dimensions were:

  • Width: 300 mm
  • Length: 420 mm

However, the actual conditions were different.

One side had an embedded steel plate extending about 400 mm.

The other side extended about 410 mm, but 20–30 mm of remaining concrete reduced the usable installation area.

These conditions required additional structural preparation before installing the crane runway system.

Answer: Yes.

But the crane system must be designed according to the existing building.

For this Mexico project:

  • Wall-side runway beams used chemical anchor connections.
  • Column-side supports required embedded plate preparation.
  • Additional steel structures were designed where corner supports were missing.

The crane was adjusted to the factory, instead of forcing the factory to fit a standard crane.

Challenge 2: Inclined Columns Reduced the Crane Working Area

During measurement, engineers found that the middle columns leaned inward. The available space in the center area was smaller than both ends.

A normal crane span design could create several problems:

  • Crane collision with columns
  • Reduced travel distance
  • Limited working coverage

Answer: Because the maximum building width is not always the usable crane operating width.

Engineers need to consider:

  • Column position
  • End clearance
  • Wheel position
  • Trolley movement area

For this project, the crane span was calculated based on the real working space.

Challenge 3: Uneven Support Heights Affected Rail Installation

In another workshop area, engineers found uneven concrete corbels.

Measured elevations:

  • Left corbel: 6.707 m
  • Right corbel: 6.753 m

The height difference was nearly 50 mm. Although this difference may seem small in normal construction, it can affect crane operation.

Uneven rail levels may cause:

  • Crane drifting during travel
  • Uneven wheel loading
  • Increased mechanical wear

The engineers recorded each support point and provided adjustment requirements before installation.

Answer:

Because overhead cranes travel on fixed rails.

If the rails are not level:

  • The crane may not move smoothly.
  • Wheels may carry different loads.
  • Long-term operation becomes unstable.

The engineers recorded every support point and provided adjustment requirements before installation.

Customized Crane Design Solution

After the site survey, we did not directly choose a standard crane model.

The engineers reviewed the actual working conditions first:Workshop structure, Mold weight, Lifting frequency, Required lifting height, Operator working habits,

Because every workshop is different, the crane design also needed to be different.For example, the available space limited the crane layout. The mold handling process required stable positioning. The building structure also affected the crane load design.

Based on these factors, we designed two HD single-girder overhead cranes for the customer.

Equipment Quantity Main Application
HD Single-Girder Overhead Crane 1 Set Heavy mold lifting and replacement
HD Single-Girder Overhead Crane 1 Set Mold positioning and transfer

The final solution matched the customer's production process, workshop conditions, and daily operation needs.

10 ton and 5 ton single girder overhead crane for sale from Chinese Crane Manufacturer in China

Similar overhead crane project for Agentina for your reference 

Solution 1: 10 Ton HD Single-Girder Overhead Crane

After checking the workshop structure and production requirements, we selected a 10 ton HD single-girder overhead crane for the heavy-duty handling area.

The crane needed to handle large molds while reducing the load on the existing building structure. It also needed enough lifting height and smooth movement for daily mold replacement operations.

The 10 ton crane is mainly used for:

  • Heavy mold lifting
  • Mold replacement
  • Large component handling

The customer mainly uses this crane when changing production molds and moving heavy components between working areas. The double-speed hoisting system also helps operators complete positioning work more smoothly.

Item Specification
Capacity 10 Ton
Crane Type HD Single-Girder Overhead Crane
Span 24.13 m
Lifting Height 9.81 m
Working Duty A5
Hoisting Speed 0.8/5.0 m/min (Double Speed)
Hoist Traveling Speed 2–20 m/min (VFD Control)
Power Supply AC 380V 50Hz
Control Mode Wireless Remote + Wired Pendant
Working Temperature -20°C to +40°C

During the site survey, we found that the workshop structure had limited load capacity.

A standard LD single-girder crane would increase:

  • Crane dead weight
  • Wheel pressure
  • Load on concrete supports

After checking the structure and calculating the wheel loads, our engineers selected the HD single-girder design.

The reason was simple:

The customer needed a 10 ton lifting capacity, but the existing building could not take unnecessary additional loads.

Compared with a conventional design:

  • Main girder height was reduced by about 22%.
  • Maximum wheel pressure was reduced by about 5%.
  • The crane still met the L/800 stiffness requirement.

The final result:

  • Lower load on the workshop structure
  • Better use of available lifting height
  • Better fit for an existing factory building

This is why we selected the HD crane instead of a standard LD crane for this project.

5 Ton Overhed Crane


Solution 2: 5 Ton HD Single-Girder Overhead Crane

After reviewing the workshop layout, we found that this working area had stricter space limitations.

The customer needed a crane for daily mold handling, but the workshop had limited headroom. The crane also needed to move smoothly and position molds accurately during production operations.

Based on these requirements, we selected a 5 ton HD single-girder overhead crane with a compact structure and better lifting height utilization.

The 5 ton crane is mainly used for:

  • Mold handling
  • Production line transfer
  • Precision positioning

During daily operation, the crane helps operators move molds safely between different production stations and complete positioning work more efficiently.

Item Specification
Capacity 5 Ton
Crane Type HD Single-Girder Overhead Crane
Span 19.191 m
Lifting Height 6.12 m
Working Duty A5
Hoisting Speed 0.8/5.0 m/min (Double Speed)
Hoist Traveling Speed 2–20 m/min (VFD Control)
Crane Traveling Speed 3–30 m/min (VFD Control)
Power Supply AC 380V 50Hz
Control Mode Wireless Remote + Wired Pendant
Working Temperature -20°C to +40°C

During the survey, we found that the injection molding workshop had limited vertical space.

The upper area included:

  • Roof trusses
  • Lighting equipment
  • Existing workshop structures

A traditional underslung trolley crane would take more vertical space and reduce the available hook height.

The HD single-girder crane uses a side-mounted trolley design.

This allows the trolley to move beside the box girder instead of hanging below it.

The result:

  • More compact crane structure
  • Higher effective lifting height
  • Better use of existing workshop space

For this project, the HD design helped the customer handle molds within the limited workshop height without modifying the building structure.

Mold Handling Requirement: Precision Control

During the workshop survey, we found that the customer frequently needed to flip molds during production.

The heaviest mold: Up to 7 tons

The mold needed to move between:

  • Horizontal position
  • Vertical position

This operation was not only about lifting capacity.

The crane also needed to provide:

  • Stable lifting
  • Smooth movement
  • Accurate positioning

For mold handling, precise control is important. A crane that only runs at one fixed speed may make the mold swing during movement and increase positioning time.

Answer: Because mold handling requires accuracy, not just lifting power.

A fixed-speed crane may cause:

  • Mold swinging
  • Difficult alignment
  • Longer mold replacement time

Operators then need to rely heavily on manual inching and experience.

A better solution is to control the speed according to each operation stage.

Electric control box  of 10 ton overhead cranes -Yuantai Cranes

Electric control box  of 10 ton overhead cranes -Yuantai Cranes 

Control Solution

The crane uses two lifting speeds.

  • High speed: Used for normal lifting operations. It helps operators move molds quickly to the required height.
  • Low speed: Used for final positioning and mold alignment.
    Low-speed setting: 0.8 m/min

The speed ratio reaches: 6.25:1.

This allows operators to switch between fast lifting and precise positioning smoothly.

The crane is equipped with a Schneider VFD control system.

The system helps achieve:

  • Faster movement when the crane is unloaded
  • Automatic speed reduction under heavy loads
  • Smoother crane travel

With the wireless remote control, operators can move and position molds more easily without manually adjusting the crane speed.

Electrical System Optimization

During the site inspection, we also checked the customer's existing crane electrical system.

We found that the existing crane used an integrated control design, where the crane travel and trolley travel controls were combined.

This design created several problems:

  • More cable movement during operation
  • More difficult maintenance
  • Higher risk of electrical failure

For a production workshop, unstable electrical control can affect daily operation and increase downtime.

For the new cranes, we designed a separate electrical control system.

The improvements included:

  • Independent electrical control units
  • Aviation-grade connectors
  • Protected wiring system
  • Separate hoist electrical system

This design makes each part easier to check and maintain.

The optimized electrical system provides:

  • Easier maintenance
  • Faster installation and commissioning
  • More reliable daily operation

The new design also helps reduce troubleshooting time when maintenance is required.

Project Result

After installation, commissioning, and acceptance testing, the two HD single-girder overhead cranes were put into operation in the customer's injection molding workshop in Mexico.

The cranes now support daily mold handling, mold replacement, and material transfer between production stations.

Since the system was commissioned, the customer has achieved:

  • Faster mold replacement
  • Safer handling of heavy molds
  • Less manual lifting and handling
  • Higher production efficiency
  • More stable and reliable daily operation

More importantly, we did not simply supply a standard crane.

We designed the crane system around the customer's workshop, production process, and lifting requirements.Our engineers selected the right crane structure, added variable-speed control, and provided on-site technical support from survey to commissioning.The final solution fits the factory's actual working conditions. It supports today's production and leaves room for future expansion.

Why Choose Yuantai Cranes for Injection Molding Applications?

Most customers are not crane experts, and they don't need to be.

Simply tell us:

  • What you need to lift
  • Load weight
  • Lifting height
  • Workshop layout
  • Working frequency

Our engineers will take care of the rest, including crane selection, structural analysis, customized design, installation support, and testing.We provide complete overhead crane solutions for injection molding factories and other manufacturing workshops.Send us your workshop layout or lifting requirements, and our engineering team will provide a customized crane solution based on your actual working conditions.